Gypsum Board Ceiling Installation Method Statement
O submitted technical submittal for acoustic treatment.
Gypsum board ceiling installation method statement. Proper scaffolding should be provided for installation work. The general rule for hanging ceiling drywall is to install the largest panels you can handle. Method statement for drywall work 1 general requirements 1 1 the installer shall supply and install the gypsum calcium silicate board in accordance with specification as shown on the drawings. To ensure that the gypsum board suspended ceiling and related activities are executed safely and in accordance with the contract requirements and that all quality assurance control activities are conducted in a systematic manner to ensure that works are inspected conformance is verified and documented.
Gypsum board ceiling installation method statement. The main runner or the c channel is spaced at 1200mm on center holding the framed furring channel to which the gypsum ceiling board is fixed at right angle or as manufacturer instruction. Obtain necessary clearances and approvals from engineers including mep clearance. Civil method statements tags.
The long sides of the panels. This method statement for false ceiling describes the details of the installation of suspended gypsum board and tile ceiling with the use of metal framings in the project. Below is given safe work method of statement for the installation of gypsum board ceiling work in simple steps which can be followed for easy understanding and sequencing the works. Submission documents 2 1 technical data.
Perimeter angle of 25mm x 25mm is set on all sides of the ceiling giving a base for gypsum board ceiling or as manufacturer instruction. Masuzi june 13 2018 uncategorized leave a comment 77 views. This method statement provides the control sequence of construction and methodology that will be used for the installation of dry wall with resilient material as an acoustic treatment for walls inside the area of treatment by m s optima international. This procedure is applicable to the following works associated with.
This also outlines the health and safety hazards involved and include the guide on how to do the process safely. Beam grid ceiling tiles baffles gypsum board method statement for false ceiling works post navigation method statement for erection and dismantling of slab formwork method statement for grp lining and ladder installation in water tanks. Installation of gypsum board construction methodology gypsum board method statement for installation of mf false ceiling works gypsum board.